Stonhard Delivers High-Performance Solution for Lithium Battery Production Facility

Battery Manufacturer Faces Challenges in New Production Facility

A lithium battery manufacturer required a durable epoxy flooring solution for its brand-new 84,000 sq. ft. production plant in North Carolina. Facility managers were concerned about long-term performance and needed a system that could handle joint movement without cracking or delamination. 

Stonkote GS4 epoxy flooring delivers a chemical-resistant and easy-to-clean surface for battery production facilities.

Stonhard crews installed Stonkote GS4 epoxy coating, ensuring a durable surface for the new production space.

Stonhard Installs Durable Epoxy Coating Flooring

Stonkote GS4, an epoxy coating designed for chemical and wear resistance, was selected for this industrial flooring project. Known for its long-term durability, abrasion resistance, stain resistance, and gloss finish, Stonkote GS4 not only enhances light reflectivity but also delivers a clean, professional appearance.

Stonhard completed surface preparation in just three days, ensuring the new concrete substrate was ready for the installation of the coating system. High-strength grout was used to patch the surface, followed by the application of a high-solids primer. After allowing the floor to cure, the epoxy coating was installed. Joints were then cut and filled with backer rod and a flexible polyurethane sealant, a method that ensures the coating remains intact and resistant to cracking caused by joint movement. The result is a durable, high-performance floor that meets the demands of a bustling industrial environment while maintaining a polished, professional look.

For battery manufacturers, Stonhard delivers critical protection against corrosive agents while providing smooth, easy-to-maintain surfaces that enhance operational efficiency and simplify facility maintenance. With unmatched technical expertise and a wide range of flooring solutions, Stonhard won the project despite fierce competition. The installation was successfully completed within the client’s tight 11-day timeline.